Bulli Zone Substation

Sunday January 1, 2012

Construction of a new 470-square metre control building, including cable basement and associated works and the installation of new HV conduits at Endeavour Energy’s Bulli Zone Substation commenced in December 2011. This stage of the project is due for completion in late 2012. Future stages of the project will include the demolition of the existing switchyard and construction of new transformer enclosures, access road, refurbishment of the existing control room and site remediation. The staged completion date for the overall project is late 2015. Project value $4.8m.