Construction commenced at deakin.one
Friday February 26, 2021
26 February 2021
Project Update: Construction commenced this week at deakin.one with drilling of the piers.
The team is drilling on average 15 piers per day, including reinforcement and concrete. There’s a total of 112 piers, so it won’t take long to complete.