Holbrook Hospital Update

Thursday January 2, 2003

Refurbishment of the Holbrook Hospital for the NSW Department of Commerce is progressing well, with the following works undertaken:

October
Groundwork to external slabs, floor preparation and structural steel was completed. Roofing, windows, wall cladding and door frames were completed. Brickwork, rough-in of services and drywalls & ceilings were substantially completed.

November
Floor finishes, render and joinery have commenced. External concrete slabs will be poured. Brickwork, rough-in of services and drywalls & ceilings will be completed this month.

The project is due for completion in mid 2004.  Project value $1.93m